|
Unknown
|
Flight Report A Cessna Skymaster 337, N111AT, was mobilized from Huntsville International Airport,
Huntsville, AL to Picayune Municipal Airport, Picayune, MS on 30 Jan 2003. This aircraft was outfitted with an Optech
ALTM 1210 LIDAR system. Mission planning for the project determined that 103 flight lines would be needed to successfully
cover the specified area, including three control lines. These lines would be flown at a 120-knot ground speed, 1250
meters above ground level and would take approximately 37.5 hours to complete. Three GPS base stations supplied and
operated by Sea Systems Corporation were used to support precise positioning and orientation of the ALTM's sensor head
during the entire duration of flight. The GPS base stations were Trimble 5700 receiver units utilizing Zephyr Geodetic
antennas. Each GPS base station was located within the boundary of the project area. The actual local flight times and
duration of flights were controlled by fuel consumption of the aircraft, safety of flight operations in the particular
airspace and during times when the GPS constellation was most favorable, producing the highest number of satellites
visible in the best geometric configuration relative to the GPS receivers onboard the aircraft as well as at the master
stations on the ground. A standard of flying with no less than 7 satellites visible and a PDOP (position dilution of
precision) of less than 3.0 was adopted. The initial aerial survey was completed over the course of 8 days. Data
collection started around 23h30 UTC on Saturday, 01 February 2003. Flightlines completed during this flight were lines
one through 12. On 01 February the flight commenced at 02h50 UTC and completed lines thirteen through twenty-nine.
The flight on 02 February began around 23h10 UTC and collected lines thirty through thirty-eight. A second flight was
then flown beginning around 02h30 UTC on 03 February and completing lines thirty-nine through forty-five. On 04
February the flight commenced around 22h40 UTC and covered lines forty-five through fifty-four. The second flight
followed a refueling stop around 02h30 UTC and completed lines fifty-five through sixty-six. The flight on 05 February
covering lines 67-69 and 97 through 100 began around 22h10 UTC and ended around 00h30 due to weather. The final day of
initial data collection occurred on 08 February. Two flights were flown this day. The initial flight began around
00h46 UTC and covered lines seventy through eighty-eight and line 103. The second flight began around 22h19 UTC and
completed lines 67-69, 89-96 and 101 and 102. This completed the initial LIDAR data collection for the project and the
ground crews continued in their remaining work in and around the project area. The aircraft and personnel involved
during the LIDAR portion of the survey were demobilized on the night of Sunday, 09 Feb 2003. Following a preliminary
examination of the collected data it was determined that one flight was required to refly some of the collected lines.
A Cessna Skymaster 337, N111AT, was mobilized from Huntsville International Airport, Huntsville, AL to Picayune
Municipal Airport, Picayune, MS on 30 Mar 2003. This aircraft was outfitted with an Optech ALTM 1210 LIDAR system.
Data collection commenced at approximately 22h35 UTC and constituted reflying lines 5, 9, 86-88, 92 and 103 for various
technical reasons. This completed the LIDAR data collection for the project and the ground crews continued in their
remaining work in and around the project area. The aircraft and personnel involved during the LIDAR portion of the
survey were demobilized on Monday, 31 Mar 2003. A Cessna 210, N732JE, was mobilized from Huntsville International
Airport, Huntsville, AL to Picayune Municipal Airport, Picayune, MS on 11 FEB 2003. This aircraft was outfitted with
a RC30 Camera and AGFA Pan 80 film. Mission planning for the project determined that 40 flight lines would be needed to
successfully cover the specified area at the various flying altitudes. These lines would be flown at 4800 feet above
ground level with 80/30 overlap, 9030 feet above ground level with 60/30 overlap, 12000 feet above ground level with
80/30 overlap and would take approximately 18 hours to complete. Three GPS base stations supplied and operated by Sea
Systems Corporation were used to support precise positioning and orientation of the photo centers during the entire
duration of flight. Each GPS base station was located within the boundary of the project area. The actual local flight
times and duration of flights were controlled by fuel consumption of the aircraft, safety of flight operations in the
particular airspace and during times when the sun angle was most favorable. The aerial survey was completed over the
course of 3 days. Data collection started around 11h19 local on Tuesday, 11 February 2003. Flightlines completed on
this day ranged from one to nine at 4800 feet and one through five at 9030 feet. Collection recommenced around 9h47
local on 12 February. Lines completed during this flight were six through 12 at 9030. On 13 February collection began
around 09h26 local and lasting through 15h00 local. Lines collected during this flight included ten to eighteen at 9030
and ten through twenty-three at 12000 feet. This completed the photo collection for the project and the ground crews
continued in their remaining work in and around the project area. The aircraft and personnel involved during the photo
portion of the survey were demobilized during the afternoon of Thursday, 13 February 2003. Upon inspection of the film
it was determined that reflights would be necessary. On 23 February 2003 a Cessna 335, N918AA, was mobilized from
Huntsville International Airport, Huntsville, AL to Picayune Municipal Airport, Picayune, MS outfitted with a RC30
Camera and AGFA Pan 80 film. Collection took place between 09h34 and 12h31 local. Lines six, eight and nine at 9030
and lines sixteen, seventeen, twenty and twenty-three at 12,000 were reflown. GPS/IMU Data Processing Upon completion of
the flight portions of the project the GPS data was post processed for quality and backed up. For redundancy and accuracy
purposes, the airborne GPS data were processed from the base stations using GrafNav from Waypoint Consulting, Inc.
Results from the LiDAR N111AT JD_032F01 Final Solution. The final solution for this flight is PR43/PR43 FWD/REV. The
REV solution from PR15 and the FWD solution from B154 matched fairly well with the final, but are not used in the final
due to the long baseline distances. PECK was not processed since an incorrect point was occupied during the flight. This
solution is considered good. DLW 10 April 2003 JD_032F01 Final Solution. The final solution for this flight is PR43/PR43
FWD/REV. The FWD solution from both PR15 and B154 matched very well, within a couple of centimeters, with the final,
but are not used in the final due to the long baseline distances. The REV solutions from PR 15 and B154 were both off by
about 10 cm. PECK was not processed since an incorrect point was occupied during the flight. This solution is considered
very good. MWB 2 April 2003 JD_032F02 Final Solution The final solution for this flight is PR43/PR43 FWD/REV. The
combined solution from PR15 matched, but adds noise. The FWD solution from B154 matched but is not used in the final due
to the long baseline distance. PECK was not processed since an incorrect point was occupied during the flight. This
solution is considered very good. MWB 2 April 2003 JD_033F01 Final Solution The final solution for this flight is
B154/PR15 CMB/CMB. The solutions from PR43 matched, but added more noise. PECK processed ok and could have been processed
to match, but it was not needed as part of the solution. This solution is considered very good. MWB 2 April 2003
JD_033F02 Final Solution The final solution for this flight is B154/PECK/PR15 CMB/CMB/CMB. All solutions from all bases
processed very well. PR43 matched, but was not used because of the added noise. This solution is considered very good.
MWB 2 April 2003 JD_035F01 Final Solution The final solution for this flight is B154/PR43 REV/CMB. The REV solution from
PR19 matched, but added noise. The FWD solutions from B154 and PR19 did not process as well as the REV solutions.
PR05 did not process well in either direction, probably because of baseline distance. This solution is considered good.
MWB 2 April 2003 JD_035F02 Final Solution The final solution for this flight is B154/PR19/PR43 CMB/CMB/CMB. All solutions
from all stations processed very well. PR05 was not used because of baseline distance. This solution is considered very
good. MWB 3 April 2003 JD_036F01 Final Solution The final solution for this flight is PR05/PR19/PR43 REV/REV/CMB. All
solutions from the three stations processed well. The FWD solutions from PR05 and PR19 could have been used with some
work. B154 needed some reprocessing, but was not needed because of baseline distance. This solution is considered good.
MWB 3 April 2003 JD_038F01 Final Solution The final solution for this flight is PR05/PR19/PR43 CMB/CMB/CMB. All solutions
from all stations processed well. B154 was not needed because of baseline distance. This solution is considered very
good. MWB 3 April 2003 JD_039F01 Final Solution The final solution for this flight is PR05/PR19/PR43 REV/CMB/CMB. All
solutions from all stations processed well. The FWD from PR05 processed ok, but was rather noisy. B154 was not needed
because of baseline distance. This solution is considered very good. MWB 3 April 2003 JD_089F01 Final Solution The final
solution for this flight is PR17/PR17 FWD/REV. Station PR43 did not process well. External noise seems to be influencing
the data. PR17 processed well during the data collection times of the flight. The data were noisy during the
mobilization from the airport to the work site. This may be due to baseline distance. This solution is considered good.
MWB 9 April 2003 These trajectories were used in the processing of the inertial data. The inertial data were processed
using PosProc from Applanix, Inc. This software produces an SBET ("smooth best estimate of trajectory") using the GPS
trajectory from GrafNav and the roll, pitch and heading information recorded by the POS (Position and Orientation System).
Results were favorable for all flights and errors are estimated to be less than 5cm.
Respectfully Submitted, MD Atlantic Technologies, Inc. Darrick L. Wagg, P.Geo. 15Jun2004
Data Processing Report Data collection of the survey areas resulted in a total of 103 flight lines covering the project
area including 3 control lines. The tapes, flight logs, raw air and ground GPS files were then taken to the office for
data processing using Realm, a LiDAR processing software package from Optech. Processing began by downloading these files
into a Realm database. Although Realm has the capability to perform GPS processing and to utilize real-time inertial data,
MD Atlantic utilizes other methods of obtaining this information as Realm only has the capability to produce a single-baseline
solution. For redundancy and accuracy purposes, the airborne GPS data were processed from two base stations using GrafNav
from Waypoint Consulting, Inc. The agreement between a minimum of two solutions checked or combined between a minimum of
two stations was better than 10 cm in each of X, Y, and Z. These trajectories were used in the processing of the inertial
data. The inertial data were processed using PosProc from Applanix, Inc. This software produces an SBET ("smooth best
estimate of trajectory") using the GPS trajectory from GrafNav and the roll, pitch and heading information recorded by the
POS (Position Orientation System). Realm uses the SBET to generate a set of XYZ data points for each laser return. Data can
be segregated based on the first- and last-pulse information. First and last pulse files were created during the processing
of this dataset. This project's data were processed in strip form, meaning each flight line was processed independently.
Processing the lines individually provides the data analyst with the ability to QC the overlap between lines. Raw lidar data
are processed within the lidar manufacturer's software to produce XYZI files. These files are output in UTM coordinates
with a corresponding Ellipsoid Height value. Output XYZI files from Realm were converted from UTM co-ordinates with GRS80
ellipsoid elevations into State Plane Coordinate System (NAD83) with NGVD29 orthometric heights using the U.S. Army Corps
of Engineers' Corpscon, version 5.11.08. Corpscon utilizes the Geoid96 model for the ellipsoid to orthometric height
conversions. The resultant XYZI files were subsequently imported into a project, on a per pulse basis, using TerraScan
(Terrasolid Ltd.) where each line was checked against adjacent lines. This check revealed an issue with the calibration
numbers being used for the system. Further investigation led to the understanding that calibration parameters would have to
be determined on a line-by-line basis. Though uncommon, this situation is not unheard of with airborne laser terrain mapper
systems. Once the calibration parameters for each line were determined and the data recalculated, the data was checked against
the control and validation points across the project area. The results of these checks showed a bias in the dataset for all
lines, save for 97 and 99, of -1.2 U.S. Survey Feet. It was determined that an adjustment to correct for this bias would be
best for the dataset. A subsequent check of the DEM found it fitting the validation and control points well. See LiDAR DEM
Quality Control Report for results. The data from each line was then combined and a classification routine performed to
determine the rough surface model. This initial surface model was then reduced using MD Atlantic's proprietary methods to
create the final bare-earth dataset. A Triangular Irregular Network (TIN) was generated using the final surface data.
Contours were then created from the TIN for use in performing a quality control of the surface. The LiDAR data were taken
into a stereo environment and melded with photogrammetric data. Breaklines were subsequently compiled along hydro features
to support the contour generation.
Respectfully Submitted, MD Atlantic Technologies, Inc. Darrick L. Wagg, P.Geo. 03Jun2004
ARC Grids Processing Procedures Processing of the ARC Grids and Tins began by merging dtm models that overlaid the tile
boundary. The merged dtm file was then imported into an ARC/Info point coverage that was utilized as an input source during
the tin processing. Along with the ARC/Info point coverage, the ARC Generate file of the breaklines was also utilized as an
input source during the Tin process. The final input during the Tin process was to use the tile polygon boundary to clip the
Tin file. Once the Tin was created, the generation of the 5ft Grids was processed through the ARC/Info TINLATTICE command.
The final product is a Grid with 5ft postings, clipped to the tile boundary. The final step to having deliverable Grids was
to ensure that the projection was defined for each Grid. The ARC/Info command PROJECTDEFINE was utilized for this process.
ARC Shape Files Processing Procedures The first step in the Shapefile process was to import the Microstation DGN files into
ARC/Info coverages. Once the files are in an ARC/Info coverage file format, then a Join was performed on the Arc Attribute
Table with the ACODE Info file, which is produced during the IGDSARC translation. The next step is to add any new items that
are to be converted over to the ARC shapefile DBF. Once all the applicable items are properly calculated, then all
unnecessary items are dropped. The ARC coverages are then exported as a shapefile, which will contain only the necessary
fields in the tables. Respectfully Submitted, MD Atlantic Technologies, Inc. Jesse Gregg, GIS Technician
|